How East West Rail would benefit Oxford
With around 5,000 businesses employing over 100,000 people, Oxford’s importance as an employment hub is clear – as is its global reputation for excellence. East West Rail could ease the pressures of constrained growth, opening up access to new homes, office and lab space – making it easier to live and work in the area. With regular and more affordable services from the local area to the likes of Milton Keynes, Bedford and Cambridge, Oxford would be better connected with other economic hubs across the UK. An upgraded station would have more capacity and the improved railway connections would provide wider access to talent, reduce congestion and improve air quality locally.
East West Rail would make it easier for people to enjoy days out, such as visiting designer outlet shopping centre Bicester Village; the Second World War codebreakers’ home at Bletchley Park; Stadium MK which is home to Milton Keynes Dons Football Club and also a concert venue able to host 35,000 people; or Universal United Kingdom Resort near Bedford which will be served by a new station at Stewartby. East West Rail will also connect with five major rail routes, enabling people to visit attractions and destinations further afield.
What's next for Oxford?
What work is required in the Oxford area?
Network Rail has appointed a masterplanning team to design a long-term solution for Oxford station. Alongside a new western entrance, the vision would also include a new main eastern entrance and improved onward transport links, with facilities designed to cater for future growth. The upgrades, which aim to improve capacity, accessibility and the overall passenger experience, will also help accommodate the increase in passengers expected from East West Rail (EWR). However, further work will be required to enable the full EWR service. Network Rail is also proposing to reopen the Cowley Branch Line for passenger services, which would free up platform capacity at Oxford station and allow EWR train services to terminate at the station.
To support efficient and reliable operations, we are also working with the wider rail industry on additional measures, including potential stabling options in the Oxford area and a new northbound passing loop near Kennington to support freight and passenger movements. We are continuing to assess whether further track work is needed between Oxford station and Oxford North Junction to provide sufficient capacity for EWR services.
Work is continuing with the train operator and local stakeholders, including those involved in the proposed Oxford United stadium at Kidlington, to identify improvements at Oxford Parkway. These include a new active travel hub, improved pedestrian access and safer crossing facilities. A new workforce accommodation building, a rail systems compound and replacement multi-storey car parking are all proposed within the existing north station car park. The proposals also include diverting high-voltage power cables, raising the West of Gosford and Water Eaton footbridge to provide electrical clearance, and widening the railway corridor south of the station to accommodate a potential turnback siding. This would allow trains to reverse direction if EWR opens before the separate Cowley project is complete.
We do not plan for EWR services to call at Islip and no changes to this station are required, however, a passing loop would be constructed to the north-east of Islip to serve the westbound track to the south of the railway, which would allow faster trains to overtake slower services. The southern extent of the passing loop would be lined by hedgerows to provide visual screening. A permanent compound and track access point are proposed at the eastern end of Islip station car park to provide routine and emergency access to the passing loop. Hedgerows and landscaping would provide visual screening, while the junction with Bletchingdon Road would be widened to accommodate large vehicles.
Construction of the passing loop would be supported by two temporary satellite compounds: one north of the station car park, accessed via the existing station entrance, and a second further north, accessed via the existing track from Middle Street.
Why are we proposing this work?
We previously consulted Oxford communities on proposals to add new platforms, deliver new infrastructure south of the station, and make improvements within the station itself. A new platform and entrance on the western side of the station are already being delivered as part of Network Rail’s Oxford Corridor Phase 2 scheme. Network Rail is also proposing to reopen the Cowley Branch Line for passenger services, which would allow trains to terminate and turn back south of Oxford station and free up extra capacity for future EWR services.
The rebuilt section of the line between Bicester and Bletchley was completed by the East West Rail Alliance and handed over to Network Rail in December 2024 and is now part of the national network.
Chiltern Railways was announced as the operator of the line in March 2025 and is working closely with the Department of Transport to finalise these arrangements and start services as soon as possible.
We’re currently consulting on what work is required at Oxford Parkway and Bicester Village stations to serve the additional passengers resulting from the new EWR services. One of the main considerations is how to improve access to both stations via more sustainable forms of transport as this would affect any need for the expansion of the existing parking at these stations. You can see our latest proposals as part of our 2026 Consultation.
What’s next?
The rebuilt section of the line between Bicester and Bletchley was completed by the East West Rail Alliance and handed over to Network Rail in December 2024 and is now part of the national network.
Chiltern Railways was announced as the operator of the line in March 2025 and is working closely with the Department of Transport to finalise these arrangements and start services as soon as possible.